Resource Planning comes with its own area in the administration. You reach it through Administration > Planning > Settings. There you define company-wide how projects are labeled in the planning views, whether planning on tasks is allowed and who is informed about changes to plannings.
Note: This article describes the new Resource Planning, which appears in ZEP as the main menu item Planning. If your main menu also contains Work packages, you are still working with the previous resource planning. Its features are described in Feature Overview – Scheduling and Work Packages.
Display Name for Projects
The setting for the display name of projects in Resource Planning defines how ZEP labels a project in the planning views. It affects the lanes, the filters, the sidebar, the bars and the notifications about changed plannings, not the project data itself.
Three options are available:
Abbreviation shows the project code only. This keeps the lanes narrow and suits you if the codes are well known in your company.
Description shows the full project name. That is self-explanatory but needs more room.
The third option combines both and puts the description in brackets after the abbreviation.
The setting applies to all employees in the tenant, not per person.
Planning on Tasks
The setting Allow planning on tasks defines whether your company may also plan on the tasks of a project. To do so, select the checkbox and save. It is switched off by default, and planning then happens on the project as a whole.
The setting allows you to show the task level per project. You do this in the planning on the project detail page with the icon whose tooltip reads Show tasks. How this works in detail is described in Planning Views – Resource Planning. Projects whose task level is already shown keep it even while the setting is switched off, and you can keep planning on tasks there.
Note: As long as a planning or a placeholder demand sits on a task, the setting cannot be deselected. ZEP then states the number of affected projects and links them. Delete the plannings and placeholder demand on the tasks or move them to the project level. After that, the setting can be deselected again.
Remarks on Plannings
The setting Record remarks for plannings adds the field Comment to the form of a planning. Planners can note up to 255 characters there, for example the work content or an agreement. The comment appears in the tooltip of the bar. The setting is switched off by default. While it is off, ZEP hides the field and the comments in the planning.
Notification About Changed Plannings
The setting Notify employees when their scheduling has been changed controls whether ZEP notifies the person concerned as soon as their planning changes. It is switched off by default. Activate it if the people you plan should learn about changes without having to check their own planning.
Effect
When the setting is active, employees receive a notification in ZEP as soon as someone creates, changes, or removes their planning. Clicking it takes them straight to their own planning. Without it, employees notice a change only when they open their own planning. This matters above all when several people plan or when schedules change at short notice.
Bundled Sending
ZEP does not notify on every single change. Changes are collected for one hour and then delivered as a bundle. If several projects are affected, each project appears on its own line with its period. Anyone adjusting several plannings in a row therefore does not trigger a flood of individual notifications.
Scope
The setting applies company-wide to every employee who is planned in Resource Planning. Whether someone receives a notification therefore depends only on whether the setting is active and the person is planned.
Notification About Adjustments Due to Absences
If an absence is created, changed, or deleted for a planned person, ZEP adjusts the affected plannings from today onward. For plannings in hours, ZEP distributes the planned hours across the remaining working days so that the planned effort is preserved. Plannings in percent keep their value.
With the setting Notify when an absence adjusts the planning, you choose who receives a notification about it: Department Manager (with the Locations & Departments area), Project manager with budget, and Project manager without budget. This way, the people responsible learn why bars in the planning have changed.
Permission for the Settings Area
The area is visible only to users who are allowed to view the administration in the roles and permissions matrix. Saving a change additionally requires the permission to edit the administration. If either permission is missing, ZEP hides the area or refuses to save.