Resource Planning comes with three reports. All are located in the Reports menu in the "Resource planning" group. The first compares the planning with the hours actually recorded, the second compares the available capacity of your employees with the time already scheduled. The third shows the open demand from placeholders that are not yet staffed.
Note: This article describes the new Resource Planning, which appears in ZEP as the main menu item Planning. If your main menu also contains Work packages, you are still working with the previous resource planning. Its features are described in Feature Overview – Scheduling and Work Packages.
Planning/Actual Comparison
This report compares planned hours with recorded hours, per employee and project in the selected period. It answers the question of how closely your planning matches reality. By default the result is shown as a bar chart.
Columns
Each row of the table shows one combination of employee, project, and time period. Placeholders that are not yet staffed appear as separate rows with the suffix (vacant) after their name, as long as you filter neither by employee nor by employee category.
Column | Meaning |
Employee | The planned person |
Project | The project the person was planned for |
Time Period | The time slice according to the selected scale |
Plan (h) | The planned hours |
Actual (h) | The hours actually recorded |
Deviation (h) | The difference between actual and plan |
Filters
The filters define which data is included in the report. When you open it, the bookable project statuses are preselected. You can clear that preselection.
Filter | Effect |
Time Period | The date range to be analysed |
Department | Restriction to departments, only if the Departments area is active |
Employee | Selection of individual people |
Placeholder | Selection of individual placeholders that are not yet staffed |
Projects | Selection of individual projects |
Project status | Restriction to particular project statuses |
Project duration | Projects that overlap the period, start within it, or end within it |
Project category | Restriction by the category of the project |
Employee category | Restriction by the category of the person |
Only projects with tasks | Limits the report to projects whose task level is shown |
With planning only | Hides rows without a planning |
Billable/non-billable | Limits the report to billable or to non-billable times |
Level | Project level (default) or Task level, mandatory |
Scale (Table) | Aggregation by day, week, or month, mandatory |
The filters Level and Only projects with tasks appear as soon as planning on tasks is allowed or a project shows its tasks. On the Project level, all plannings and bookings of a project count together. On the Task level, the report splits projects with tasks shown into one row per task, and plan and actual then refer to that task. Plannings and bookings without a task sit in the row of the project.
Example: A person is planned on the project level but books their time on the task Concept. On the task level, the plan then sits in the project row and the actual hours in the row of Concept. For a comparison per task, plan on the task that time is also booked on.
Key Figures
Above the table you find key figures summarising the selected period: the total planning, the booked actual, and the deviation in relation to the plan. The deviation carries a sign, so you see at a glance whether too much or too little was booked. In addition there is planning accuracy, which is meaningful only under certain conditions.
Key figure | Meaning | Appears only |
Planning accuracy | How close the recorded hours are to the planning, as a percentage | if neither billability nor "With planning only" nor the Placeholder filter is set |
The reason for this restriction is a factual one: as soon as you look at part of the recorded times only, planning accuracy could no longer be related meaningfully to the full planning. In that case the tile does not disappear. It stays in place and names the filter that renders it unusable, so you see straight away which filter to withdraw in order to get the key figure back.
Planned Capacity Utilization
This report compares available capacity with scheduled hours, per employee and department in the selected period. It therefore does not show how well you planned, but how much room your team still has.
Columns
The table is sorted by department and lists one person with their time slice per row.
Column | Meaning |
Department | The department of the person |
Employee | The planned person |
Time Period | The time slice according to the selected scale |
Available (h) | The capacity left after absences and public holidays |
Scheduled (h) | The hours already planned |
Still available (h) | The remaining capacity, negative in case of overbooking |
Filters
The filters are deliberately leaner than in the planning/actual comparison because this report is calculated on an employee basis only. Available are Time Period, Employee, and Departments. The department filter and the department column require the Departments area to be active. If the area is deactivated, ZEP reports by employee only. There is no project, category, or billability filter here.
Key Figures
The key figures summarise the capacity situation in the period: the available capacity, the share scheduled of that capacity, the total still available as the balance of free and overbooked time, and the over/under booking as the number of employees above and below plan. In the matrix view, values above one hundred per cent are marked as overbooked.
Open Demand
This report shows the hours of all placeholders not yet staffed in the selected period, by project, department, price group and skill. It shows where staff is still missing and how urgently. By default the result is displayed as a bar chart. How placeholders are created and staffed is described in Creating Plannings – Resource Planning.
Columns
Each row of the table shows one placeholder with its time period, with one row per skill if several skills are required.
Column | Meaning |
Project | The project the placeholder belongs to |
Placeholder | The name of the placeholder |
Identifier | urgent if the demand starts within two weeks at the latest or is already running, overdue if it lies completely in the past |
Fillability | How many employees you could staff it with cover the demand in full: several available (three or more), one to two available, or no one available |
Department, Price group | From the target profile, only if the Departments area is active and prices are stored |
Skill Category, Skill | The required skills, only with the permission to view skills |
Start, End | The first and the last day of the demand |
Time Period | The time period according to the selected scale |
Open demand (h) | The open hours in the time period |
Demand per skill (h) | The hours per required skill. A placeholder counts once per skill here, so the total can exceed the open demand |
Filters
The filters narrow down the period, the projects and, where the Departments area is active, the departments. In the table you can additionally filter by price group, skill category and skill. The project name leads to the planning of the project, provided you may see it. From there you staff the placeholder directly.
Key Figures
Above the table, Total open demand gives the open hours in the period, with the number of placeholders concerned below it. of which no one is available gives the hours of placeholders for which no suitable person covers the demand in full. of which without department shows demand whose target profile names no department. The chart view compares the open demand by project, department, price group, skill category or skill.
Location in the Reports Menu
The three reports are located differently, depending on whether they are meaningful on an employee or a project basis.
Report | Employee reports | Project reports |
Planning/Actual Comparison | yes, grouped by employee | yes, grouped by project |
Planned capacity utilization | yes | no |
Open demand | no | yes |
The planning/actual comparison is two separate views at its two menu locations: filters and favourites apply per entry point, and a favourite carries the axis in its name. Planned capacity utilization always calculates against the capacity of a person. There is therefore no project-related equivalent. The closest thing on the project side is the open planned hours, which you read as a single figure directly in the planning view of the project. Open demand is available under the project reports only. It is visible to anyone who may evaluate the project-related reports of Resource Planning.
Relation to the Previous Reports
The previous resource planning provided a report of the same name, planning/actual comparison, plus reports on work packages and workload. With the switch, the planning/actual comparison and planned capacity utilization take their place.
Note: Only one of the two resource plannings is active in your account at a time. Old and new reports therefore never appear side by side. How the switch works is described in Switching from the Previous Resource Planning.


